德國旗艦級鐵道工程,因鋪錯一千公里信號纜線,將延宕五年完工

斯圖加特廿一 (Stuttgart 21) 鐵道工程,德國的 (也是歐洲的) 一項重大基建,因鋪錯約1000公里的信號纜線,將延至2031年完工。

鋪錯原因是原以為是全數位化電纜,就趕在最終設計完成前就開始先鋪。差不多完成後才發現,還有貨車需要傳統訊號,須保留傳統訊號。有估計新設450個訊號設備將增加工程成本 4500 萬歐元。

斯圖加特廿一本來是為迎接 21 世紀,於1990年代啟動規劃、2001核定,原計畫2019開通,預算45億歐元。自2010年動工至今已16年,成本已超過110億歐元。反覆的延誤已將此宏大計畫變成德國基建的恥辱。

Germany’s flagship rail megaproject delayed to 2031 after over 1,000 km of cables laid incorrectly

https://brusselssignal.eu/2026/06/germanys-flagship-rail-megaproject-delayed-to-2031-after-over-1000-km-of-cables-laid-incorrectly/

10 June 2026

The errors occurred because cabling work began before the final technical planning for the new digital signalling system was complete.

One of Germany’s (and Europe’s) most ambitious and controversial infrastructure projects, Stuttgart 21, has suffered yet another major setback.

The full commissioning of the new underground through-station and digital rail hub will now not occur until the end of 2031 — five years later than the most recent target and twelve years behind the initial planned opening.

According to an investigation by broadcaster SWR, Deutsche Bahn laid more than 1,000 kilometres of cables and cable ducts incorrectly in a rush to meet earlier deadlines.

A large majority of this infrastructure must now be replaced.

The errors occurred because cabling work began before the final technical planning for the new digital signalling system was complete.

The project is intended to be the first fully digitised major railway system in Germany, with routes and trains equipped with the European Train Control System (ETCS) and controlled by digital interlockings, a pioneering pilot scheme.

However, four years ago Deutsche Bahn realised that freight trains without ETCS equipment will continue to operate for years in the outer sections of the rail junction.

As a result, conventional signals must be retained alongside the new digital technology in those areas. This late discovery forced the railway to install additional kilometres of cabling and ducts after much of the work had already been completed to the original digital-only plan.

Additional problems include faults in the emergency power supply and construction defects on station platforms and flooring. These combined issues have made the previous goal of a 2026 partial opening impossible.

One railway expert told SWR that the constriction site looked more like a “pigsty”.

He estimated that installing the 450 new signals alone will cost around €45 million. Deutsche Bahn has confirmed the need for dual equipment but has declined to comment on the exact extra costs.

Politicians in Baden-Württemberg have reacted with fury.

Baden-Württemberg’s Minister-President Cem Özdemir (Greens) described the project as slowly becoming “a national joke”.

He demanded “reliable figures” and clear answers from Deutsche Bahn on when individual stages and the entire project will finally be completed. “It has to end at some point,” Özdemir said.

Transport Minister Winfried Kretschmann and local leaders described the latest delay as “unacceptable” and demanded full transparency from Deutsche Bahn, which has so far declined detailed comment and referred questions to an upcoming press conference.

Originally approved in 2001 with a planned opening in 2019 and a budget of around €4.5 billion, Stuttgart 21 has become a symbol of German infrastructure failure.

Costs have now surged past €11 billion, while repeated delays have turned the prestige project into a national embarrassment.

There were also at least €726 million in EU grants for the project as well.

Stuttgart 21 was never only a transport project. In 2001, the city of Stuttgart acquired the majority of the freed-up railway land, totalling 109 hectares, for nearly €460 million.

The ambitious plan was to create several new residential and urban quarters, including the Rosenstein district, with minimal restrictions for investors.

Those developments can now only begin years later due to the repeated delays. Since missing the original 2019 opening target, Deutsche Bahn has already been forced to pay millions of euros in contractual default interest to the city, a sum that continues to grow with every year of postponement.

The latest fiasco comes as Germany struggles with chronic problems in major public works, from the BER airport debacle to repeated rail infrastructure issues.

Critics argue that political pressure for rapid “green” and “digital” modernisation, combined with poor project management, continues to produce expensive and humiliating results for taxpayers.

The Bund der Steuerzahler (Taxpayers Association) has long criticised the project as a bottomless pit. A spokesman warned that further billions from the federal budget and Deutsche Bahn are being poured into what he called a “classic example of unchecked project mismanagement.”
2026-06-11 14:29 發佈
大媽一去, 德國飄零
德國製造光環褪去
一看就知道是故意延宕想加錢的藉口
拆了再建,又增加GDP啊,這是“德政”!
德國曾經的歐盟領頭羊,國鐵DB十多前年還是以準時著稱,月台不檢票,高鐵ICE一等車箱真皮座椅,現在拉垮到一個匪疑所思的地步,連漢莎航空也不少問題,一堆龍頭德企都受不了,連根拔起加大對中投資力。



高鐵調度錯站台,倒退嚕這種重大安全問題都能發生。
Curtis_l wrote:
德國曾經的歐盟領頭羊...(恕刪)


在網路上看到一篇文章,是旅德大陸人跟德國人吐嘈說你們比我們更像共產主義。主要是說重稅高福利

德國累進稅制 14%-45% 看起來還滿正常
但是年收入一萬兩千歐元(約44萬台幣)以上就進入14%、七萬歐元(約250萬台幣)就到42%
對比起來臺灣是大概60萬台幣才進入12%、500萬台幣才進入40%
所以德國從普通職員往上爬升到小主管的路上,稅負就會急遽上升

然而德國的生活費用,一個月一千歐日子只夠過得緊巴巴
所以德國又有很多補助

結果就是累死累活的,跟不工作生一堆小孩的難民家庭比,手頭還沒比人家寬裕多少。那誰還要積極任事。

網文不知實情如何,但是收容很多難民造成社會福利負擔,應該是有的。
內文搜尋
X
評分
評分
複製連結
Mobile01提醒您
您目前瀏覽的是行動版網頁
是否切換到電腦版網頁呢?