哥偶然看到您在2023年說:
既然你們這些五毛這麼專業 怎麼不分析分析中製柴油發電機是有多爛
為什麼泰國打死不接受
結果2025年9月泰國新聞報導:
The Royal Thai Navy (RTN) has signed the revised agreement with defence contractors in China to resume Thailand's submarine procurement project, which has stalled for some time over a dispute over engine specifications.
The new deal, which was approved by the Thai cabinet on Aug 5, was signed at the headquarters of China Shipbuilding & Offshore International Co (CSOC) in Beijing on Tuesday, according to a post on RTN's official Facebook page on Thursday.
The government was represented by Adm Jirapol Wongwit, the commander-in-chief of the RTN, while CSOC's executive vice president, Liu Song, signed on behalf of China.
The revised contract allows construction of the Yuan-class S26T submarines ordered by the navy to continue with significant changes, said Adm Jirapol. The most critical modification is the replacement of the German-made MTU396 diesel engine -- which could not be exported due to restrictions imposed in 2021 -- with a Chinese-made CHD620 diesel engine.
The revised contract also extends the construction deadline by 1,217 days, or about 40 months, from the original timeline. Delivery of the first submarine is now scheduled for late 2028.
The procurement contract was originally signed as a government-to-government deal in 2017, with a price tag of 13.5 billion baht.
泰國皇家海軍(RTN)已與中國國防承包商簽署了修訂後的協議,以重啟泰國潛艇採購項目。該項目因發動機規格爭議而停滯了一段時間。
據RTN週四在其官方Facebook頁面上發布的一則貼文稱,這項新協議於8月5日獲得泰國內閣批准,並於週二在中國船舶及海洋工程國際公司(CSOC)位於北京的總部簽署。
泰國政府代表是RTN總司令吉拉蓬•翁維特上將,而中國船舶及海洋工程國際公司執行副總裁劉松代表中方簽署了協議。
吉拉蓬上將表示,修訂後的合約允許海軍訂購的元級S26T潛艇繼續建造,但需進行重大修改。最關鍵的修改是用中國製造的CHD620柴油引擎取代德國製造的MTU396柴油引擎(該引擎由於2021年實施的限製而無法出口)。
修訂後的合約也將建造期限比原定時間延長了1217天,約40個月。首艘潛艦的交付時間目前定於2028年底。
該採購合約最初於2017年作為政府間協議簽署,總價值為135億泰銖。
============================================================
您要不要幫哥科普一下 怎麼泰國皇家海軍又改變了心意用
中國製造的CHD620柴油引擎取代德國製造的MTU396柴油引擎